Alley Improvement Master Plan
This Master Plan was adopted by Council in September 2017. The plan will require 48 years to reconstruct 19.5 miles of alleys with the remaining 17.5 miles of alleys are scheduled to receive slurry seal coat every 10 years. The first round of slurry will be distributed over Years 1, 2, & 3, and repeat in Years 10, 20, 30, & 40.
Below are the two maps which indicate which alleys are to be slurried and which alleys are to be reconstructed along with the corresponding assigned year in the Improvement Master Plan.
We are currently in Year 6 for reconstruction and working on Year 3 for slurry.